Welcome Customer !

Membership

Help

Shandong Runchuang Environmental Protection Equipment Co., Ltd
Custom manufacturer

Main Products:

hbzhan>Products

Shandong Runchuang Environmental Protection Equipment Co., Ltd

  • E-mail

    941593506@qq.com

  • Phone

    1516964627915169646279

  • Address

    Building 67, 14278 Jiankang East Street, Kuiwen District, Weifang City, Shandong Province

Contact Now

RCYTH-0.5 Hengshui Runchuang Environmental Protection Township Domestic Sewage Treatment Equipment

NegotiableUpdate on 01/31
Model
Nature of the Manufacturer
Producers
Product Category
Place of Origin
Overview
The domestic sewage treatment equipment of Runchuang Environmental Protection Township in Hengshui City adopts the world's biological treatment process and MBR membrane treatment process, which integrates the removal of BOD5, COD, and NH3-N, and is currently the most efficient sewage treatment equipment. It is widely used for domestic sewage in villa communities and residential areas.
Product Details
brand Runchuang Environmental Protection Processing & Customization yes
processing capacity 10m³/h rated voltage 380v
rated power 1.5kw Diameter of water outlet pipe 110mm
Inlet pipe diameter 110mm

Hengshui CityRunchuang Environmental Protection Township Domestic Sewage Treatment Equipment

In order to meet the requirements of water environment governance within the prescribed time, many places may be "forced" to significantly increase investment in a short period of time. The "Ten Measures for Water Quality" have set clear and concise goals for the national water environment quality, and the demand for water environment governance will still exist. In the three months from May to July, the market released over 29 water environment governance projects with a total investment of far exceeding 65.8 billion yuan. In terms of funding arrangements for water pollution prevention and control in the same year, relevant departments will provide 100 million yuan in support for each "inferior" section of the battle, and also provide varying degrees of support for other key tasks.

Breaking through water has become a top priority for ecological environment protection in various regions. In a sense, water environment governance projects are no longer just a project, they are driven by regional environmental governance. From a regional perspective, the East and South China regions have high population density, heavy industrial pollution, and developed water systems, and market demand is expected to be fully released. Several cities listed as "lagging behind in meeting standards" will increase investment and prioritize special governance actions related to improving water quality in assessment sections, such as sewage interception pipelines, new expansion and upgrading of sewage treatment plants.

Hengshui CityRunchuang Environmental Protection Township Domestic Sewage Treatment EquipmentProduct Overview

The RC-AO integrated sewage treatment equipment adopts the world's biological treatment process, which integrates the removal of BOD5, COD, and NH3-N, and is currently the most efficient sewage treatment equipment. It is widely used in hospitals, blood stations, high-end hotels, villa communities, and residential areas for the treatment of domestic sewage and similar industrial organic sewage. The treated effluent can achieve:

GB 18918-2002 Pollutant Discharge Standards for Urban Sewage Treatment Plants. Field applications have shown that the RC-AO series integrated sewage treatment equipment is a device with excellent treatment efficiency and easy management.

Scope of Application

The treatment of domestic sewage in residential areas, hospitals, schools, villa communities, hotels, nursing homes, and other places. The treatment of production wastewater from aquatic processing plants, livestock processing plants, fresh milk processing plants, and garbage transfer stations.

Product Features

1. The RC-AO series sewage treatment equipment can be placed above the ground or buried below the surface. The surface can be used as green or square land, so the equipment does not occupy surface area, does not require building, and does not require heating and insulation.

2. The RC-AO series sewage treatment consists of secondary tanks, with the first stage being a reinforced concrete structure with a relatively deep burial depth, and the other group being a steel structure with a relatively shallow burial depth. The steel structure pool adopts the domestic * interpenetrating network anti-corrosion coating for anti-corrosion. It is an interpenetrating polymer formed by the interpenetrating of a rubber network and a plastic network. It is resistant to acid, alkali, salt, gasoline, kerosene, aging, abrasion, and rust. After applying the coating, the anti-corrosion life of the equipment can generally reach more than 30 years.

3. The AO biological treatment process in the RC-AO series sewage treatment equipment adopts a push flow biological contact oxidation tank, which has better treatment than mixed or two-stage series mixed biological contact oxidation tanks. And it has a smaller volume than activated sludge tanks, strong adaptability to water quality, good impact resistance, stable effluent quality, and will not cause sludge expansion. At the same time, a new type of elastic three-dimensional packing material was used in the biological contact oxidation tank, which has a large actual specific surface area and is convenient for microbial biofilm formation and detachment. Under the same organic load conditions, it has a higher removal rate of organic matter than other packing materials and can improve the solubility of oxygen in water.

4. Due to the use of a biological contact oxidation tank in the AO biological treatment process, the volume load of the packing is relatively low, and the microorganisms are in the self oxidation stage, resulting in less sludge production. In addition, the moisture content of the sludge produced by the biological contact oxidation tank is much lower than that of the sludge produced by the activated sludge tank. Therefore, the amount of sludge generated by the RC-AO series sewage treatment equipment is relatively small, and generally only needs to be discharged once every 90 days.

5. The RC-AO series sewage treatment equipment not only adopts conventional blower noise reduction measures (such as vibration isolation pads, mufflers, etc.), but also sets up new sound-absorbing materials on the inner wall of the blower room, so that the noise level during equipment operation is below 50 decibels, reducing the impact on the surrounding environment.

6. The RC-AO series sewage treatment equipment is equipped with soil deodorization facilities. It utilizes reinforced concrete structure to set up improved soil and air distribution pipes in the upper space of the pool body. When the odorous components dissolve in the water contained in the soil through the soil layer, they are then transferred into the soil due to surface adsorption and chemical reactions, and finally decomposed by microorganisms to achieve deodorization.

7. The RC-AO series sewage treatment equipment is equipped with a fully automatic electrical control system, which has good reliability. Therefore, there is no need for dedicated personnel to manage it, only monthly and quarterly maintenance and upkeep are required.

Power Calculation

serial number

Device Name

quantity

Actual quantity (units)

Actual running quantity (units)

Single unit power

(kw)

Total operation

Power (kW)

Daily running time (h)

Power consumption (kWh)

1

Aeration machine

2

1

3.0

6.0

20

60

2

Sewage lifting pump

2

1

3.0

6.0

20

60

3

sludge return pump

2

1

1.1

2.2

4

4.4

total

14.2

124.4

cost calculation

1) Power cost

If the electricity fee is calculated at 0.60 yuan per kilowatt hour, thenE1=124.4 × 0.60=74.64 yuan/d

2) Calculation of operating costs

E=E1=74.64 yuan/d

The sewage treatment capacity is 300 tons/day, equivalent to a sewage treatment cost of 0.2488 yuan/ton of water.

The drug cost is 0.03 yuan per ton, and the total sewage treatment cost per ton is 0.2788 yuan.

Technical Specifications

The removal of organic pollutants and ammonia nitrogen by RC-AO series sewage treatment equipment mainly relies on the AO biological treatment process in the equipment. The working principle is that due to the high concentration of organic matter in sewage, microorganisms are in a state of gas deficiency. At this time, microorganisms are facultative microorganisms, which convert and decompose organic ammonia in sewage into NH3-N. At the same time, they use organic carbon as an electron donor to convert NO-2-N and NO-3-N into N2, and also use some organic carbon sources and NH3-N to synthesize new cellular substances. So the tank not only has a certain function of removing organic matter, reducing the organic load of subsequent aerobic tanks to facilitate nitrification, but also relies on the high concentration of organic matter in the raw water to complete denitrification and ultimately eliminate nitrogen eutrophication pollution. At level O, although the concentration of organic matter has significantly decreased, there is still a certain amount of organic matter and high NH3-N present. In order to further oxidize and decompose organic matter, and ensure smooth nitrification while carbonization is complete, an aerobic biological contact oxidation tank with low organic load is set up at level O. In the O-level pool, aerobic microorganisms and aerobic bacteria (nitrifying bacteria) are mainly present. Aerobic microorganisms decompose organic matter into CO2 and H2O; Autotrophic bacteria (nitrifying bacteria) use inorganic carbon produced by the decomposition of organic matter or CO2 in the air as a nutrient source to convert NH3-N in wastewater into N-2-ON, N-3-ON, and the effluent from O-grade tanks is returned to the * tank, providing electron acceptors for the * tank and ultimately eliminating nitrogen pollution through denitrification.

Equipment installation, debugging, and maintenance

1. Installation: This equipment consists of two sets of tanks, one set is a reinforced concrete structure tank body, and the other set is a steel structure tank body. The reinforced concrete pool body is buried underground, and the steel structure pool body can be buried below the floor or installed on the floor. The civil engineering condition drawings for two sets of pool foundations are provided by our company, and it is required that the excavation width around the perimeter should be at least 600mm larger than the equipment plan size.

2. According to the installation diagram, use a crane to lift the steel structure pool into place. The installation must be carried out under the guidance of our technical personnel, and the position and direction of the box cannot be placed incorrectly. Our company is responsible for the pipeline connection between the pools.

3. After installation, the equipment must be filled with water and tested for leaks at all pipeline interfaces before soil can be filled around and in the gaps of the equipment, and the ground should be leveled. The control lines of the electrical control cabinet should be connected to the equipment, and the electrical control cabinet should be connected to the power lines. Pay attention to the direction of the fan and water pump when wiring.

4. After the installation of the equipment, it is necessary to ensure that there is no water accumulation on the rainy ground, and no heavy objects should be placed above the steel structure pool. Equipment generally does not evacuate internal sewage to prevent groundwater from floating the equipment.

5. Debugging: Our company is responsible for the debugging work. In order to speed up the debugging progress, bacterial strains can be added. To avoid bacterial loss, the water inflow can be reduced and the fan can be started for aeration until a layer of orange yellow biofilm grows on the packing, which is the completion of packing film hanging. Then, the water inflow can be increased to the rated flow rate. After completing the membrane coating of the packing material, the microorganisms in the biological tank are acclimated by gradually reducing the amount of aerator, so that the biological tank is in a state of hypoxia and the microorganisms on the packing material become facultative microorganisms. Then adaptively operate the microorganisms until they meet the design requirements.

6. Equipment maintenance and upkeep: Our company has established a regular maintenance system for AO series sewage treatment equipment for customers, with the main vulnerable component being the water pump. Regularly check the looseness of screws in various parts of the fan and water pump, the tightness of the packing box, the temperature of the bearings, and the quality and amount of lubricating oil to ensure that all parts are normal. At the same time, check the dosage and remaining amount of disinfectant, and adjust the dosage and supplement disinfectant if necessary. The fan and water pump should be maintained and repaired every 5000-8000 hours of operation.

Quality Assurance Commitment

To ensure the quality of the bidding equipment, the following commitments are made:

1. The bidding equipment shall comply with the Chinese Environmental Protection Product Technical Conditions Standards and Enterprise Standards.

2. Strictly follow the contract requirements and provide products that meet design standards and meet quality standards.

3. Strictly inspect and control the incoming quality of raw materials, components, and outsourced parts.

4. We will insure the equipment provided during the manufacturing, transportation, and loading/unloading processes. In the event of an accident, we will promptly replace or repair the equipment free of charge as requested by the purchaser until they are satisfied.

5. If any missing parts or other reasons cause the loss of components during the unpacking process, we are responsible for promptly and free of charge filling the missing parts.

6. Any quality issues that arise during the installation and debugging of the equipment should be addressed first, and then responsibilities should be clarified. If it is our fault, we will bear the responsibility and compensate the demander for any direct economic losses suffered, all based on meeting the requirements of the project schedule.

After sales service commitment

All products sold by our company come with a one-year warranty, lifetime warranty, free design and selection, and free technical consultation.

  • Assist customers in selecting suitable matching equipment models.
  • Provide technical information related to the equipment and be responsible for guiding installation and debugging.
  • Provide information on raw material suppliers.
  • Free training for operators and provision of technical consultation.
  • Undertake the quality responsibilities stipulated in the Quality Law of the People's Republic of China.
  • During the warranty period, if any problems occur under normal use, our company will unconditionally provide unlimited service to customers, and even replace the equipment.
  • Product maintenance: Respond within 24 hours after receiving a repair report and promptly dispatch maintenance personnel to the scene to solve the problem.
  • Free development of operating procedures for customers and free training of operators.

The company has received multiple product awards and has been selected for quality Service Integrity AAA enterprise, national consumer satisfaction brand, quality inspection National standard products, ISO9001-2016 quality system certification, outstanding contribution to promoting the development of green, low-carbon, energy-saving and environmental protection industries Made significant contributions to the sewage treatment issues of enterprises of all sizes across the country.

The company's main business includes medical sewage treatment equipment, domestic sewage treatment equipment, industrial wastewater, washing, breeding, slaughtering, food, printing and dyeing, tourism areas, urban and rural sewage transformation and treatment, and other water treatment equipment processes. It has a small footprint, low investment, and stable effluent standards. Welcome new and old customers to visit and purchase at the factory.

Currently, the scale of water environment governance projects is gradually expanding and transforming into comprehensive systems. As Professor Wang Kaijun from the School of Environment at Tsinghua University said, "Water environment governance has shifted from pursuing engineering results to focusing on environmental effects, and the main battlefield of water pollution control has also shifted from point source control to comprehensive watershed management." This integrated project of aquatic systems, which involves fish swimming in shallow bottoms and clear waters with green banks, is also due to the increasing demand for capital and service capabilities of water environment governance enterprises from larger scales and more perspectives.

These changes can provide opportunities for businesses' products and services. Industry experts point out that less than 29% of the water related fields covered by the "Ten Measures for Water" can be directly included in the supply side of the industry. In the next five years, investment space in multiple sectors, including water environment governance projects and water ecological environment restoration, will exceed 3 trillion yuan. Projects such as black and odorous water treatment and sponge cities will bring extension possibilities to this trillion level industrial chain.



Equipment picture: