Detailed installation tutorial for submersible thrusters
Pre-installation preparation
1Before receiving the goods, check whether the product is intact and undamaged, whether the appearance of the host, guide rod, blade, etc. is deformed, and whether the components are complete.
2Check whether the nameplate specifications and parameters of the equipment meet the requirements, and whether the equipment installation instructions, certificates of conformity, and other documents are complete
3Equip professional electricians and installers on site to check whether the wiring meets the installation requirements and whether the site has met the installation conditions
4For the convenience of maintenance, it is recommended to pay attention to the absence of obstacles in the installation pool to avoid affecting later maintenance and repair
5Install positioning devices where necessary to ensure correct reassembly and positioning on site
Detailed installation tutorial for submersible thrusters
1According to the design drawings, determine the position of the equipment, find the embedded parts based on the position, check whether the size of the embedded parts meets the requirements, and draw lines to determine the position of each bolt hole
2Usually, the main engine and propeller blades are packaged separately for shipment. Therefore, when the equipment arrives, the blades need to be installed. First, adjust the angle of the blades according to the working conditions. Insert one blade into the hole of the hub from above, connect it to the hub with screws, tighten the screws, and to facilitate the installation of the second blade, rotate the hub180Then install the second blade using the above method.
3Install the guide rod and hanger, lift the impeller with a hand crank, and slowly and evenly lower the impeller. The lifting process must run slowly and evenly. Insert the square guide rod into the water and ensure that the equipment is installed in place
4After installing the equipment, it is necessary to conduct regular trial runs before turning it on. After connecting the power supply, test whether the equipment can operate normally. First, check whether the power cable is connected correctly and whether the impeller rotation direction is correct