    Nanjing Hefei Anqing Changzhou Nanchang Jiujiang Guangzhou Shenzhen Jinhua Hangzhou Ganzhou Shangrao Chengdu Qingdao Jinan Wuhan Shanghai Tianjin Taiyuan Wenzhou Ningbo Zhengzhou Changsha Fuzhou Xiamen Nanning Guilin. Haikou. Shijiazhuang Huai'an Liuzhou Lanzhou Lianyungang Taizhou. Nantong Dongying Suzhou Guizhou Taizhou Deyang Wuxi Zhou Kou Xuzhou Beijing

Contact Now

Non excavation repair of urban underground pipelines

NegotiableUpdate on 03/30
Model
Nature of the Manufacturer
Producers
Product Category
Place of Origin
Overview
Non excavation repair of urban underground pipelines, UV cured lining repair is a process of first tightly adhering a resin soaked hose to the inner wall of the pipeline to be repaired through methods or processes such as pulling and compressing air, without changing the position of the repaired pipeline. Then, using the UV curing property of the resin inside the hose, a UV lamp is placed in the inflated hose and controlled to walk at a certain speed inside the hose, gradually curing the hose from one end to the other, closely adhering to the inner wall of the pipeline to be repaired, forming a hard "pipe in pipe" structure, so that the underground pipeline that has been damaged or lost its conveying function can be repaired in situ.
Product Details

The non excavation repair of underground pipelines and the construction of non excavation repair of municipal pipelines in Nanpai, Jiangsu Province provide mobile services nationwide and cover construction cases in cities of all sizes in China. It can protect the environment, save resources and characteristics, without the need to dig roads, and will not cause garbage; The repair construction period is short (curing time can reach 1m/s). The impact on the lives of surrounding residents is relatively small. currentlyNon excavation repair of urban underground pipelinesIn some old urban areas of cities, leakage, damage, and even breakage of the underground drainage system often occur due to the long service life of the drainage pipeline system, lack of maintenance, and corrosion of soil and water media. In this case, it is necessary to repair the drainage pipeline. With the development of non excavation technology, the repair of drainage pipelines can also be carried out without excavating or excavating the surface less, reducing the impact on the environment and citizens' livesvery smallCompared with traditional excavation restoration, non excavation restoration has many advantages and has been widely used.

Non excavation repair of underground pipelinesAcceptance Criteria

1. Appearance inspection

After repair
1.1 All lining pipes should undergo an internal visual inspection, and the inspection data should be included in the completion file.

1) Inner lining pipes with an inner diameter of less than or equal to 800mm should be inspected using closed-circuit television, with images as the basis for visual inspection;

2) Inner lining pipes with an inner diameter greater than 800mm should be manually inspected after cooling, and image data should be left at the defect location.

1.2 The appearance inspection results shall comply with the following regulations:

1) No cracks, holes, dry spots, detachment, burn points, weak zones, or visible leakage phenomena;

2) It should be tightly attached to the old pipeline, with smooth inner walls and no obvious circular folds;

3) The number of local uplifts in a well section should not exceed 2, and the height of the uplifts should not exceed 2% of the inner diameter (ball passing method inspection);

4) The end incision should be flat, and there should be no water leakage in the fitting gap;

5) When repairing locally, the defective area should be covered with *.

2. Wall thickness measurement

2.1 All lining pipes should undergo wall thickness measurement, and the measurement records should be included in the completion file.

1) Two ends of each lining tube should be measured, and four evenly distributed measuring points should be selected for each end;

2) It is advisable to use a thickness gauge for measurement; When measuring with a steel caliper, the accuracy should reach 0.1 mm.

2.2 The wall thickness measurement results shall comply with the following regulations:

1) The average wall thickness of any end should not be less than the design wall thickness;

2) The small wall thickness at either end should not be less than 90% of the design wall thickness.

3. X120-UV Portable UV Curing Repair System Curing Parameter Table

At high speeds, diameter dependent light sources should be used in conjunction with high-performance ultraviolet lamps. The temperature sensor should have complete functions and operate well, and the temperature of the middle lamp holder sensor should reach between 80-130 ℃. If the temperature is less than 80 ℃, the curing speed should be reduced for adjustment.

The suggestions given here are based solely on personal experience. Special construction sites may require lower curing speeds. Therefore, we do not assume any guarantee responsibility for any details. Please adjust the speed according to real-time temperature feedback during construction!Non excavation repair of urban underground pipelines